|
Safety-
A June 13, 2007 Newsday article by Magdalene Perez
quoting a New York State Comptroller’s Report stated,
“growing delays and ballooning costs are setting back efforts
to improve transit security in the metropolitan area.” “The
MTA needs to address this problem before it spirals out of
control,” said New York State Comptroller Thomas Di Napoli.
“The percentage of construction tasks behind schedule has
nearly doubled in the past eight months alone.”
Of sixteen (16) security projects the MTA
invested in since the September 11 attacks, only two (2) have
been completed, the report stated, six (6) fewer than originally
planned. Eight (8) projects were one or more years behind
schedule.
The plans, some of which are still in the
design phase, call for reinforcing the structure of train
stations, transit hubs and bridges and tunnels, as well as
improving fire safety, evacuation measures and electronic
security and surveillance.
Costs for the projects also have risen,
with the first phase of improvements now $224 million more than
originally planned. The total cost of completing all the
security improvements is estimated at $1.3 billion.
The delays can be blamed on unforeseen
issues caused by working with a transit system that is more than
100 years old, the agency said. “We’re dealing with
retrofitting a 19th_century system with a 21st-
century technology to respond to security threats that were
never contemplated before,” said MTA spokesperson Jeremy
Soffin.
Is
there any question that this constitutes a major safety concern
for everyone living on Long Island!
A major debate has been raging in
Washington over whether cities can order dangerous cargo to be
rerouted around their population centers. Many large cities
including Washington, Chicago, Philadelphia, Boston and
Baltimore have introduced rail-rerouting ordinances. These large
cities are not comfortable with the current safety standards
promulgated by the Federal Government. |